Supplementary Information Tables

Status report on projects operating with specific Treasury Board approval

Project Name
and Phase
Original
Estimated Total Cost
(dollars)
Revised
Estimated Total Cost
(dollars)
Actual
Total Cost
(dollars)
2018-19
Main Estimates
(dollars)
2018-19
Planned Spending
(dollars)
2018-19
Total Authorities
(dollars)
2018-19
Actual Spending
(dollars)
Expected
Date of
Close–out
Fleet Operational Readiness
Polar Icebreaker 800,000,000 1,297,762,043 58,217,819 2,776,695 2,776,695 3,938,681 1,495,446 2024-25
Shore-Based Asset Readiness
Communications Control System Equipment Replacement 15,704,958 47,789,000 47,836,269 0 0 84,809 84,809 2018-19

Note: dollar amounts exclude both the goods and services tax (GST) and the harmonized sales tax (HST).